Under the Party Wall Act 1996, you must serve a party structure notice or line of junction notice at least two months before starting work on or near a party wall, shared wall, or boundary, while a notice of adjacent excavation requires just 14 days. Your neighbour then has 14 days to respond — if they don't reply, they're treated as having dissented, which means surveyors must be appointed to prepare a party wall award before work can begin. If they consent, you can proceed once the notice period has passed.